EXPERIENCE: |
|
|
|
||
Problem: Redesign a large cold storage distribution facility to be fully refrigerated and accommodate efficient future expansion.
Solution: During the design build system phase of the construction, it was necessary to look at the future requirements of the cold storage facility. The task was to design an industrial refrigeration system that was not only capable of refrigerating 135,000 sq. ft. of existing facility, but one that would accommodate an additional 35,000 sq. ft. addition on the existing footprint, and then an additional 170,000 sq. ft. back-to-back facility to fill out the building site.
The first phase of the design build system had the full capacity liquid recirculator.